Construction Progress

 
 

 

Healthcare Facilities

• Tertiary Care & Teaching Hospital
• Professional Medical Suites
• Laboratory
• Research Centre and Medical Suites

» September 2013
» June 2013
» March 2013
» December 2012
» September 2012
» June 2012
» March 2012
» December 2011
» September 2011
» June 2011
» March 2011
» December 2010
» September 2010
» June 2010

 


September 2013

City International Hospital officially opens from 24 September 2013.

 

June 2013

The actual site progress rate is 100%

» Top

 

March 2013

The actual site progress rate is approximately 99%

» Top

 

December 2012

The actual site progress rate is approximately 92%

» Top

September 2012

The actual site progress rate is approximately 87.90%

» Top

 

June 2012

Installation of window frame and floor screeding are on going. Elevators have been imported and being installed. Transformer and generator set have been installed.

» Top

 

March 2012

Major brickworks are on going followed by plastering works. Mechanical and electrical conduits and risers are also being installed. Door frame and window frame installation are in progress.

» Top

 

December 2011

Completion of structural works of City International Hospital. The project is using Post-Tension Slab as its structural for added strength to cater for medical equipment and to shorten the duration of construction works.

» Top

 

September 2011

City International Hospital: Concrete casting is completed at Zones 1 and 1a. Concrete casting is in progress at Zones 1b and 2a. Formworks are being carried out at the various zones.

» Top

 

June 2011

City International Hospital: Concrete casting is in progress at Levels 2 and 3. Removal of formworks and re-shoring is carried out at the underside of Zones 1 and 2a and at Level 2.

» Top

 

March 2011

City International Hospital: Pile caps, main lift core wall and beams at the Basement Level are completed. Stump columns, backfilling and main lift core wall are in progress at Level 1.

» Top

 

December 2010

Piling works are completed while pile-cap excavation for the sub-structure is in progress.

» Top

 

September 2010

Piling works completed.

» Top

 

June 2010

With the Construction License Approval obtained in early April, site clearance is completed and piling works are in progress.