Construction Progress

 
 

 

Healthcare Facilities

• Tertiary Care & Teaching Hospital
• Professional Medical Suites
• Laboratory
• Research Centre and Medical Suites

» September 2011
» June 2011
» March 2011
» December 2010
» September 2010
» June 2010

 


September 2011

City International Hospital: Concrete casting is completed at Zones 1 and 1a. Concrete casting is in progress at Zones 1b and 2a. Formworks are being carried out at the various zones.

 

June 2011

City International Hospital: Concrete casting is in progress at Levels 2 and 3. Removal of formworks and re-shoring is carried out at the underside of Zones 1 and 2a and at Level 2.

 

March 2011

City International Hospital: Pile caps, main lift core wall and beams at the Basement Level are completed. Stump columns, backfilling and main lift core wall are in progress at Level 1.

» Top

 

December 2010

Piling works are completed while pile-cap excavation for the sub-structure is in progress.

» Top

 

September 2010

Piling works completed.

» Top

 

June 2010

With the Construction License Approval obtained in early April, site clearance is completed and piling works are in progress.

» Top